Introduction - If you have any usage issues, please Google them yourself
(1) E importation of Arc lt; J, kgt; Establish AOE- network storage structure (2) v starting point source, ve [0] = 0, by topological sorting point for the rest of the earliest timing ve [i] (1LT ; = ilt; = n-1). if the Topography vertex orderly sequence number is less than net n vertices, a statement that net presence in Central, not for Critical Path, algorithm implementation steps to terminate or (3) (3) from the Department of v starting point, Vl [n-1] = ve [n-1], by the inverse order for the remaining topology of the latest occurrence of peak time Vl [i] (n-inversion; = IGT; = 2). (4) According to the apex of ve and Vl value for each s arc of the earliest timing e (s) and the latest starting time of l (s). If any meet the conditions of the arc e (s) = l (s), was critical activities.